Maldives Sets November 2027 Target for Thilafushi Commercial Port
The planned 60-hectare port will initially handle 390,000 TEUs a year, with a larger international quay and a separate domestic harbour.

The Maldives government is targeting November 2027 for commercial port operations at the new Thilafushi site, where the planned initial capacity is 390,000 twenty-foot equivalent units of cargo a year.
President Mohamed Muizzu reaffirmed the timetable during a visit on 1 October to review the relocation of Malé’s commercial harbour. Maldives Ports Limited officials briefed him on construction, equipment procurement and the facilities planned for the new port.
The President’s Office account of the visit sets out a 60-hectare development with separate facilities for international container vessels and domestic shipping. The full project is expected eventually to handle 1.8 million TEUs annually.
Those figures describe the planned capacity at different stages of development. TEU is a standard measure of container capacity based on a twenty-foot container; it is not a count of individual containers regardless of their size.
First Quay Section Completed
Construction of the first 100 metres of the inner harbour quay wall has been completed. Land levelling and road construction are continuing, while approximately 40 per cent of the inner harbour backfilling has been finished.
The production of precast concrete blocks for the quay wall is also progressing. Officials reported that procurement of essential machinery and equipment was underway, alongside the process of selecting a contractor for the terminal buildings.
Muizzu was received at the site by MPL chief executive Captain Hussain Shafeeq. The President described the relocation as a government priority and said ministries, companies and external partners were coordinating work on the project.
He said the new port would expand trade capacity, support business development and improve productivity. Those are the government’s stated objectives for the relocation.
International and Domestic Facilities
The initial international container quay will extend for 375 metres, with a depth of 14.6 metres. Its design allows the quay wall to be extended to 1.4 kilometres as the wider project develops.
A separate domestic quay is planned to run for approximately two kilometres. The opening equipment list includes two ship-to-shore quay cranes and one mobile harbour crane.
| Planned feature | Published specification |
|---|---|
| Port area | 60 hectares |
| Initial annual capacity | 390,000 TEUs |
| Full-project annual capacity | 1.8 million TEUs |
| Initial international quay | 375 metres |
| International quay depth | 14.6 metres |
| Domestic quay | Approximately 2 kilometres |
The government projects that the international quay will bring vessel turnaround times down to about two days. The President’s Office compared that with seven to 14 days for loading and unloading at the existing Malé Commercial Harbour.
That two-day figure is a forecast for the new facility, rather than a measured operating result. Construction, equipment delivery and terminal development remain part of the work described in the October update.
The 1 October announcement links the November 2027 target to commercial port operations at the new site. It gives separate initial and full-project capacity figures, but does not specify a completion date for the eventual 1.8-million-TEU expansion.
More from Business
Muizzu Orders Stalled Development Projects to Resume
The President’s Office says solutions have been secured for material shortages linked to Middle East conflicts, as ministers and state companies review island projects.
Maldives Expo Sets 25 October Opening with New Tourism District
The nine-day Hulhumalé event will bring resorts, guesthouses, airlines and travel businesses into a dedicated visitor-economy programme.
Maldives Subsidy Spending Exceeds Annual Budget by MVR1.26 Billion
Finance Ministry figures through 24 September put subsidy expenditure at MVR4.15 billion and the overall fiscal deficit at MVR3.36 billion.
BML Caps Monthly Dollar ATM Withdrawals at US$3,500 per Customer
The limit took effect on 1 October. The existing daily ceiling of US$1,600 per card remains in place.